Clark | Weitz | Clarkson is committed to assembling a diverse team of highly-skilled and qualified project partners, subcontractors, and suppliers that share
our commitment to quality and craftsmanship. 


The page contains important information regarding the construction procurement process and schedule for the
KCI New Terminal project. Information is subject to change. Please check back frequently for updates.

How To Get Started

Clark | Weitz | Clarkson is focused on delivering a new, world-class gateway for Kansas City, built by Kansas City.  If you are a construction subcontractor or subconsultant interested in being a part of this transformational project, please follow the instructions below to ensure you are added to our list of potential bidders. 

Questions regarding the Subcontractor Qualification Application should be directed to Bonita Alves at
301-272-8398 or
bonita.alves@clarkconstruction.com.

Completing our Subcontractor Qualification Application (SQA) is the first critical step in prequalifying to work on the KCI New Terminal Project. Required for all subcontractors and suppliers, the SQA provides us with important information about your firm, including your past experience, bonding capacity, and backlog of work. Click the SQA FORM button to begin the registration process.

Register with CWC, to ensure you receive notice of RFP postings.


CURRENT OPPORTUNITIES

Capital Electric Construction Company is  soliciting proposals for the installation and recircuiting of roadway lighting as part of the construction of the new terminal. The bidding documents for this RFP will be accessible through Bid Tracer.  To receive access to these documents please email tucker.kelsey@capitalelectric.com

A preproposal conference for this RFP will be held on Friday, May 17th  at 9:00am at the following location.

Capital Electric Construction Co.
2801 Fairfax Trafficway
Kansas City, KS 66115

Proposals are due no later than 2pm, CDT on Friday May 24 , 2019.

This solicitation is open to all interested bidders.  Capital Electric encourages participation of firms that would meet and/or exceed the project M/WBE goals.  Capital Electric is committed to achieving 20% MBE and 15% WBE participation for the project.

Clark | Weitz | Clarkson (CWC), a joint venture, is seeking a qualified firm to participate in the development of The New Single Terminal and Parking at KCI.
A Request for Proposal (RFP) is currently available for the following consulting service:

  • Needs Assessment for the Terminal Workforce Enhancement Program (TWEP)

    CWC Intends to partner with a firm to perform an independent needs evaluation of certain aspects of the TWEP and provide subsequent status reports for the duration of the project.

    The bidding documents for this RFP will be accessible through Building Connected.  To receive access to the documents, please email Matthew.Schwabauer@cwcjv.com.

    All other inquiries regarding this solicitation should also be directed to Matthew.Schwabauer@cwcjv.com.

    There will be no pre-proposal conference for this RFP.  

    Proposals are due no later than 5pm, CDT on May 21, 2019.

Scroll below the Procurement Team to view the Procurement Schedule for a list of upcoming opportunities. For additional information or to request a copy of any open RFP, please contact the appropriate estimator listed in the Procurement Schedule listed below. 

To be added to CWC’s Interested Bidders List or to find out more about upcoming opportunities, please email Matthew Schwabauer at matthew.schwabauer@cwcjv.com.


Procurement Team

Procurement Leadership

Tom Kenton headshot.jpg

Tom Kenton
Vice President of Procurement
tom.kenton@cwcjv.com
(301) 272-8280

Kelvin+Caple.jpg

Kelvin Caple
Small Business Procurement
kelvin.caple@cwcjv.com
(240) 876-8948

 
James Faddis headshot.jpg

James Faddis
Preconstruction Executive
james.faddis@cwcjv.com
(813) 636-4413

Matt+Schwabauer.jpg

Matt Schwabauer
Procurement Project Manager
matthew.schwabauer@cwcjv.com
(785) 393-7301

Wes Stith headshot.jpg

Wes Stith
Vice President of Procurement
wesley.stith@cwcjv.com
(301) 466-3158


Project Procurement Schedule

Clark | Weitz | Clarkson is committed to creating meaningful opportunities for minority- and women-owned businesses throughout the construction of the KCI New Terminal project. We will segment and package certain scopes of work to maximize the opportunities for local certified firms to contribute to this project. Tier 1 subcontractors also are required to identify opportunities for Kansas City-based M/WBE businesses to participate in their scope of work.

* The schedule below is based on preliminary information and is subject to change. Check back frequently for updates. Contact your estimator for the detailed information and updates to the scope of work.



Prevailing Wage

We anticipate that the Kansas City Aviation Department will issue a Prevailing Wage determination for the KCI New Terminal. The Prevailing Wage Act establishes a minimum wage be paid to workers on public works projects in Missouri or on behalf of state and local public entities. For specific wage rates, Prevailing Wage information is available via the Missouri Department of Labor.    

In addition, for those portions of the project that are funded in whole, or in part, with federal funds will be subject to Davis Bacon requirements.